Kitchen and bathroom renovation: the order
Renovation goes faster and costs less when the trades arrive in the right order and the decisions are made before they do.
Decide before you start
The most common cause of delay is not the building. It is the choices not yet made. Layout, fittings, tiles, taps, lights and worktops should be chosen, ordered and, where possible, delivered before the strip-out begins. Check lead times, as some items take weeks.
Check what is behind the walls
In an older house, strip-out can reveal rot, old wiring, lead pipes, failed plaster or uneven floors. Ask what allowance is in the quote for this, and how you will be told. A renovation in a Victorian house will rarely go exactly to plan, and good communication is more important than a perfect forecast.
Strip-out
Old units, fittings, tiles and flooring come out, and the room is stripped back to a state where the new layout can be marked out. Check for asbestos in materials if the house was built before 2000, particularly floor tiles, textured coatings and boards. Deal with it first.
First fix
Carpentry, plumbing, electrics and ventilation are run to their positions before the walls are finished. Pipework, cables, extractor ducts and waste pipes should be agreed on the plan. Moving a socket after plastering is far more expensive than before. Gas work must be done by someone on the Gas Safe Register, and you are entitled to ask to see their card. New electrical work must meet the safety rules and be certified.
Walls, floors and waterproofing
Plastering, boarding, floor levelling and waterproofing follow. In a bathroom, the waterproofing behind the tiles and in the shower area is critical. Ask how it is done and tested. Plaster and screed need time to dry before the next stage, and rushing that is how tiles fail.
Tiling and flooring
Tiling comes after walls and floors are ready. It is slow, precise work. Check that the layout is planned, with cuts in the least visible places, and that grout lines are straight. Flooring goes in at the stage that suits the room. A kitchen floor usually goes in before the units or under them, depending on the design.
Fitting and second fix
Units, worktops, sanitaryware, appliances, taps and electrical accessories are installed. Worktops are often templated after the units are in, which creates a gap. Plan for it. Plumbing and electrical connections are finished and tested.
Decoration and finishing
Painting, sealant, final fixings and cleaning. Sealant should be flexible and neat, and gaps should not be left. This is the moment for a snagging list.
Making decisions in the right order
Layout first, then services, then surfaces, then fittings. If you choose tiles before the layout, you may find they do not suit the space. If you choose the units before the plumbing, the sink may be in the wrong place. Working in this order keeps you from redoing choices.
Write down your decisions and share them with the builder, so everyone is working from the same list.
Living without a kitchen or bathroom
Bathrooms are the harder one, particularly if there is only one in the house. Ask whether the work can be phased so you have a working toilet and a way to wash for most of the time. For kitchens, set up a temporary corner and plan your meals. Ask honestly how many days you will be without each room.
Protecting the rest of the house
Renovation dust and footprints move through a home. Ask for a protected route from the front door to the work area, with floor covering, door closed and a dust barrier where needed. Check that the plasterers and decorators will protect finished work. Ask for the work area to be cleaned at the end of each day, so you are not living in a building site.
Where delays come from
Late decisions, long lead times, damage discovered in strip-out, trades not available when needed, and changes of mind. A realistic programme builds in room for these. Ask for the sequence in writing.
Related pages
- How long does a building project take?
- Whole-house refurbishment
- What to get in writing before work starts
Free site visit and quote
Tell us about the project at hello@margatebuilders.co.uk or on WhatsApp. We'll arrange a site visit to give you a proper quote.